Nipani wadgaon & Khokar

Key components of the project include canal intake arrangements, the construction of a balancing tank, and the establishment of pumping machinery for both raw and pure water. The system is designed to efficiently transport and treat water, ensuring adequate supply for the local community.

Client

-Yash Engineering Consultants Private Limited

Source

-Pravara Left Bank Canal

Cost

-₹61,09,16,714.00

Total Length

-39,875 meters

Capacity

-3.5 MLD (Million Liters per Day)